With an overwhelming 71% majority, the citizens of Beachwood approved Issue 3 on the May 4th primary election ballot to fund the $30 million Beachwood High School Building Improvement Project.  This project is about the facility's classroom, technology and energy infrastructure needs, which together comprise nearly three quarters of the proposed budget. The improved Beachwood High School building will soon mirror BHS's award-winning academic curriculum.

Letter from David Ostro, Board of Education President

 

 TENTATIVE CONSTRUCTION TIMELINE       

      

  June 2010 - September, 2010

  • Early design work and schematic design

 

  October 2010 - May, 2011

  • Design development
  • Construction document
  • Bidding
  • Award of bid

 

  June 2011 - July 2012

  • Renovation of 500-600-700 halls
  • Installation of mechanical systems in basement area currently occupied by band and music programs
  • New construction on 100/200 hall classroom wing, auxiliary gym/locker room, and music suite

 

  July 2012 - August 2013

  • Demolition of old 100/200 classroom wing and gym
  • New construction of media center, multipurpose room, and main office
  • Renovation of pool, south gym, dining hall, auditorium and library
  • Athletic field renovations and improvements

    

 

PROJECT PLAN IMAGES

Click on the links below to view images of the preliminary site plans

Site Plan

Exterior Main Entry

Classroom Wing

Media Center

Performing Arts Wing

South Gym Addition

Dining Hall

 

PROJECT HIGHLIGHTS

Energy/Infrastructure Upgrades (42%)

            • New mechanical room
            • State-of the-art, energy-efficient HVAC
            • Modernized, effective electrical systems

          Academics (31%)

          • New 100/200 English, world languages, and social studies academic wing
          • Renovated 500/600 math and science academic wing
          • New state-of-the-art library with two adjoining computer labs

          Community Space (13%)

          • New multipurpose meeting room
          • Remodeled cafeteria and student-run Beachwood Bistro
          • Modernized restrooms

          Fine Arts (8%)

          • New classroom, practice, storage and event-staging space adjacent to the auditorium
          • Upgraded Channel 22 Studio

          Athletics (5%)

          • Upgrade our substandard fields to address utilization needs and safety
          • Permanent outdoor restrooms, renovated concession area, improved bleachers and press box

          Administration (1%)

          • Relocating main offices to expand the 'central hub'

 

 

 

 

 

 

 